What is EVM, earned value management?
SAP Online Classes provides Best SAP training Online based on current industry standards that helps attendees to secure placements in their dream jobs at MNCs. SOC is one of the most credible ERP SAP Online training provider, offering hands on practical knowledge and full job assistance with basic as well as advanced level ERP SAP Implementation Training. At SOC ERP SAP training Online is conducted by subject specialist corporate professionals with 14+ years of experience in managing real-time ERP SAP projects.
What is EVM, earned value management?
Answer
-
At every monitoring point the planned value (PV), earned value (EV) and actual cost (AC) are monitored. PMB, performance measurement baseline is the aggregation of all planned values. Variances from baselines are determined and Schedule variance (SV) and cost variance (CV) are calculated. If earned value is equal to the planned value then the project is achieving what it is supposed to. If there is schedule or cost variance is significant, appropriate action needs to be taken to correct the slips. Estimate at completion (EAC) is estimated and compared with budget at completion. In case there is a slip, the cost consequences will be known.